Aurora was contracted by Clancy Consulting to carry out a detailed fault study analysis for a new energy centre being added to the St James Centre in Edinburgh.
Aurora’s carried out a detailed assessment of the proposed new CHP generator to the site to ensure that the subsequent 3-phase and phase-earth fault levels were within the switchgear peak and break capability, as well as checking that the system X/R ratio was acceptable and the asymmetrical duty on the system circuit breakers was acceptable.
Key Features
Client: JCP Consulting Engineers / Engie
Industry: Building Services
Plant Type: Science Park
Project: Power System Studies
Contract: Lump Sum
Date: 2018
“Aurora was appointed to undertake a fault study, protection coordination study and an earthing study for a new science park development.”