Twyver Switchgear

Protection Study and Arc Flash Study

TESCO Sites

Aurora was contracted by Twyver Switchgear to undertake a rolling program of protection coordination studies and arc flash studies across a number of TESCO distribution sites in the UK.

Aurora began by undertaking a survey of each of the main sites to identify the electrical system switchgear, transformers and associated protection relays and settings. Once this was completed, a detailed model of the electrical system was created in ETAP before individual coordination studies were carried out for each of the main protection paths

 

Key Features

Client: Twyver / TESCO
Industry: Industrial
Plant Type: Warehouse
Project: Protection Study
Contract: Lump Sum
Date: 2019/20

“Aurora was appointed to undertake a series of site survey and protection coordination study and arc flash studies for a number of sites across the UK.”