Smith Brothers

Protection Survey

Jaguar Landrover Solihull

Aurora was commissioned by Smith Brothers to carry out a site wide survey of all the main items of plant and protection settings and configuration of the Solihull manufacturing site.

The survey consisted of assessing the HV configuration of each substation, along with the switchgear, protection relays, CTs, transformer and main LV switchboards for over 60 main substations at the JLR Solihull plant. The entire survey took 2 engineers a full week to complete!

 

Key Features

Client: Smith Brothers
Industry: Industrial
Plant Type: Manufacturing
Project: JLR Solihull
Contract: Lump Sum
Date: 2020

“Aurora was appointed by Smith Brothers to carry out a site wide protection audit on the entire Solihul manufacgturing facility as part of a planned upgrade for the site”