Aurora was contracted by Hydropol to carry out a detailed earthing design for a new 33kV hydro power station in Wales.
Auroras initial scope was to carry out a soil resistivity survey, to assess the site ground conditions, and develop the overall earthing strategy, before undertaking a detailed assessment using the CDEGS design package considering, both local and transferred faults from the WPD substation. Once the initial design and study had been carried out, Aurora then produced a number of detailed earthing layout drawings.
Client: Hydropol
Industry: Power Generation
Plant Type: Hydro
Project: Design
Contract: Lump Sum
Date: 2020
“Aurora was appointed to provide technical design services for the HV and LV systems of the new hydro generation plant.”
Aurora Power Consulting are a leading independent power systems consultancy. We provide specialist power systems analysis services using software such as DIgSILENT, ETAP, PSCAD, EMTP-ATP, CDEGS and XGSLab.